Moorestown's $108 Million School Referendum: What's Being Built and When
A plain guide to the 2025 school bond, school by school, with what is already done and what comes next.
Moorestown voters approved a $108.3 million school bond in a special election on Sept. 16, 2025. The money pays for a William Allen Middle School addition, new HVAC and roofs, athletic fields and room for free, full-day kindergarten. The district is aiming to finish by the 2028 to 2029 school year.
What voters approved
There were two questions, and both passed, per the Inquirer.
- Question 1, $80.3 million: elementary renovations, the William Allen Middle School (WAMS) addition and gym, HVAC and roofs across the district, new tennis courts and stadium turf at Moorestown High School, Isenberg Gym updates and security work. It passed 2,492 to 1,302.
- Question 2, $28 million: a new operations center, high school classroom renovations, three new turf fields with lighting and traffic changes. It passed 2,310 to 1,471.
The state is chipping in $18,708,818 in aid, per the district's funding page. That aid only comes with a voter approved referendum.
What it costs a typical homeowner
The district estimated $37 a month for Question 1 and $17 a month for Question 2 on a home assessed at the average of $465,125. That is about $648 a year combined. The borrowing runs 25 years for Question 1 and 20 years for Question 2. The district also noted that debt from the last referendum, which added a wing to the high school, is paid off by 2029.
The big shuffle: who moves where
This is the part parents ask about most. Per the projects page:
- Sixth grade moves to WAMS. The two-story addition adds 13 instructional spaces, plus a full-size gym the community can use off-hours.
- Third grade moves to Upper Elementary School. UES becomes a grades 3 to 5 school, with third grade getting its own wing.
- Baker, Roberts and South Valley get renovated pre-K and kindergarten rooms, some with new in-class restrooms. Freeing up third grade space is what makes full-day kindergarten possible.
Superintendent Dr. Courtney McNeely told Patch the grade changes would happen at the same time, with the 2028 to 2029 school year as the goal.
What's already done
In her Aug. 20, 2026 back-to-school letter, McNeely said summer work covered HVAC improvements, roofing, safety and communication systems, and the high school tennis courts and stadium turf. She said the work is on track while planning continues for the larger projects.
The district's referendum site says construction goes in phases, with each package of work awarded to the lowest qualified bidder.
How to keep up
Bids, contracts and change orders go before the Board of Education. The next regular meeting is Tuesday, Dec. 15, at 7 p.m. at William Allen Middle School, per the district schedule. Our school board meeting guide covers where agendas post and how to speak. Questions about the projects can go to future@mtps.com.
Friday's Moorestown Today newsletter flags referendum contracts and school board votes before they happen, so you are not reading about them after. Subscribe here.
FAQ
- When will Moorestown have full-day kindergarten?
- The district's target is the 2028 to 2029 school year, once the referendum projects are finished and grades shift between buildings.
- How much did the referendum add to taxes?
- The district estimated $37 a month for Question 1 and $17 a month for Question 2 on a home assessed at the average of $465,125, about $648 a year combined.
Sources
- https://sites.google.com/mtps.us/future
- https://sites.google.com/mtps.us/future/projects
- https://sites.google.com/mtps.us/future/funding-strategy
- https://www.mtps.com/district_info/superintendents_message
- https://www.inquirer.com/education/moorestown-schools-bond-referendum-kindergarten-20250917.html
- https://patch.com/new-jersey/moorestown/moorestown-school-bond-referendum-projects-heres-timeline
- https://www.mtps.com/board_of_education/meeting_schedule
Get Moorestown Today in your inbox
The best of life in 08057, every Friday. Free.
Subscribe on SubstackMore from Schools & Sports
- Moorestown Wrestling 2026-27: Start Dates, Early Schedule and Life After a Region Champ
The Quakers went 14-15 last winter and sent a Region 7 champion to the state tournament. Here are this season's key dates and the matches posted so far.
- Where to Find Moorestown Quakers Game Schedules, Scores and Livestreams
Game moved? Gym changed? Here is where Moorestown High actually posts schedules and scores, and which page to trust when they disagree.